DC Regulators Set National Example for Increasing Customer Access to Expiring Federal Tax Credits for Solar
In response to the impacts of the One Big Beautiful Bill Act (OBBBA) on customers’ ability to leverage remaining federal tax credits to support solar investments to address energy affordability and clean energy goals, the Public Service Commission of the District of Columbia issued a first-in-the-nation response that provides an illustrative example of the power of U.S. states and territories in shaping clean energy policy amidst shifting federal support.
Recognizing that “without immediate, temporary process adjustments, a substantial portion of District customers may lose access to federal tax benefits, leading to higher system costs and reduced solar adoption at a time when legislative and policy mandates call for accelerated growth in distributed energy,” the DC Public Service Commission (PSC) issued an order on November 26th that establishes a temporary program to ensure utility delays do not prevent clean energy projects from qualifying for tax credits being phased out as a result of OBBBA.
The order, which aligns with recommendations of the District’s Office of the People’s Counsel, local solar companies, and IREC, establishes a “Temporary Conditional Interconnection Program (TCIP)” that addresses steps in the utility interconnection process for customer-owned solar and energy storage projects that could cause delays and result in customers of the Potomac Electric Power Company (Pepco) missing critical deadlines for eligibility for remaining federal tax credits. The program applies to all projects that have already applied for interconnection with Pepco and those that apply prior to December 31, 2025.
The TCIP requires Pepco to provide conditional approval to projects awaiting grid upgrades that are unlikely to be completed ahead of looming tax deadlines and requires the utility to procure equipment and commence construction of upgrades as early as is practical to avoid unnecessary delays. In addition, the PSC authorized Pepco to temporarily increase staffing to address the influx of projects seeking interconnection ahead of looming tax credit deadlines.
“At a crucial moment, DC regulators stepped up in a big way for customers seeking to install solar projects and qualify for expiring federal solar tax credits,” said David Golembeski, Senior Program Manager at IREC. “With this order, key tools such as the TCIP will help expedite interconnection for customers and should serve as a shining example to other states and jurisdictions.”
The order responds to the federal law H.R.1, passed in July, which rapidly accelerated the end dates for several key clean energy tax credits, including the Investment Tax Credit (ITC), which provides system owners with a tax credit equivalent to thirty percent of the cost of the system. The earliest of these deadlines, the Section 25D tax credit for customer-owned residential solar systems, is December 31, 2025. Because projects need to be “placed in service” by the relevant deadline to qualify for tax credits, interconnection delays create significant financial risk for customers who are depending on timely interconnection to receive these incentives. This risk is particularly pronounced for projects whose interconnection is contingent on grid infrastructure upgrades, which often take months or years. The DC Commission recognized these upgrades as “the primary bottleneck preventing solar systems from being placed in service in time.”
Robin Dutta, Executive Director at Chesapeake Solar and Storage Association (CHESSA) praisedthe decision, noting that “CHESSA greatly appreciates that the DC Public Service Commission recognizes the crucial benefits that solar and storage projects provide to the local grid and the urgency of bringing online as much solar and storage capacity as possible that is supported by the federal tax credit before the phase-out is complete. In particular, the Commission’s actions to accelerate interconnection timelines, especially the Temporary Conditional Interconnection Program, and ensure that systems can come online as soon as possible, is urgently needed to maximize local, clean, cheap energy for the District’s electric grid system while directly helping those who install and subscribe to those systems. This will help improve energy affordability in the District.”
The DC Department of Energy and Environment also expressed support for the decision. “We applaud the DC Public Service Commission and Pepco for taking swift actions to ensure DC residents and businesses can take full advantage of federal energy incentives,” said Richard Jackson, the Director of the DC Department of Energy and Environment. “Maximizing the use of these incentives helps strengthen our local clean energy economy and protect DC residents and businesses from rising electricity costs. We look forward to working with Pepco and the Public Service Commission on the implementation of this new program.”
IREC commends the DC Commission on responding to the urgency of rapidly expiring clean energy tax credits and establishing immediate changes that will ensure interconnection processes do not derail customers’ access to these incentives.