The New York Public Service Commission recently approved standardized utility practices to streamline the state’s transition to clean transportation. The Commission order, issued on September 19, is intended to speed up the process for connecting electric vehicle (EV) chargers to the grid and ensure that utilities can handle an increasing amount of applications for new service. 

Specifically, the order clarifies expectations for utility processing and review of EV charger projects. These new strategies will help to improve the utilities’ internal procedures and communication with applicants. 

“There will need to be significant investment in EV infrastructure to support all of the EVs that will be needed for New York to meet its zero emission vehicle targets,” said Vaughan Woodruff, Vice President—Regulatory Program at IREC. “This order is significant because it addresses the need for standardized utility processes to approve and connect EV charging projects to manage the significant increase in volume that will be required to power the state’s transportation sector.”  

The Commission’s decision follows up on recommendations from a stakeholder working group called the EV Infrastructure Interconnection Working Group (EVIIWG) that was initiated and led by the New York Department of Public Service (DPS). IREC participated in the working group, which was tasked with identifying ways to streamline the energization process. 

The Commission ruling approved the EV Application Queue Management Utility Manual, which outlines strategies that New York’s investor-owned utilities have thus far implemented on an inconsistent basis. With the modifications adopted by the Commission, the utilities will be required to standardize those practices and identify when they will be in use if they have not yet been implemented. This change will help provide clarity for applicants and ensure they are afforded consistent treatment across utility territories.

In addition to the Manual that will guide utility practices, the Commission has directed the utilities to develop a customer-facing document that will lay out the steps of the application review process and include a dispute resolution plan. This document will give customers better visibility into the process and provide a pathway to resolve issues that may arise.

The Commission also acknowledged that more work is needed to fully address the challenges discussed by the working group, such as timeline tracking and reporting as well as expanded informational resources for customers. The Order directed DPS to identify remaining issues with input from stakeholders and then develop proposed solutions for Commission review.  

Additionally, the Commission supported the advancement of an emerging practice called flexible connection—an operating agreement that accelerates the energization of new EV infrastructure and maximizes existing grid capacity by allowing new projects to limit their power demand during constrained time periods. This approach can either be utilized temporarily to get projects online at partial capacity until grid upgrades can be completed, or as a long-term strategy to make projects more responsive to grid capacity. In its order, the Commission directed the utilities to better define those options and processes in advance of future stakeholder discussions.

“IREC appreciates the actions taken by DPS Staff and the Commission to support transportation electrification in New York and looks forward to continuing to work with stakeholders to ensure that the state has cost-effective and efficient policies in place to handle increasing EV charger deployment,” Woodruff added.