Many Americans, particularly those involved in the electric vehicle (EV) industry, are concerned about the future of EVs due to federal actions. These include the revocation of funding for charging infrastructure, the elimination of EV tax credits, and efforts to rescind California’s longstanding exemption under the Clean Air Act, which has enabled many states to set stricter vehicle emissions standards. However, recent state actions and industry trends demonstrate strong opportunities for states to advance transportation electrification. 

In late June, a federal judge ordered the federal government to return funding to build EV chargers to the 14 states that sued over the initial freeze of funding under the National Electric Vehicle Infrastructure (NEVI) program. More recently, 10 states have joined California in a complaint to the federal government shortly after the administration signed a congressional resolution that would overturn California’s Clean Air Act waiver to phase out the sale of new gas-powered vehicles by 2035.  

As states continue to take a stand for EVs, so does the EV industry. Although market trends predict a decline in demand for EVs after the EV tax credit expires at the end of September, private sector investments continue. In fact, 2025 is on track to be a record year in the deployment of fast charging ports, with an estimated 16,700 ports expected to come online. Emerging industry players such as Ionna, Mercedes-Benz High Power Charging, BP Pulse, and Walmart are leading the next wave of EV charging infrastructure in the U.S. Joining this momentum, Ford announced a $5 billion investment to develop affordable EVs at scale, supported by a new EV-specific assembly line.  

Now more than ever, state regulators play a vital role in meeting the evolving needs of both the public and the EV industry. In this article, we will explore the challenges and opportunities for states to build the charging infrastructure needed to power our nation’s vehicles with electricity, highlighting the unique challenges for medium- and heavy-duty electric vehicles (MHDEVs). 

Common Bottlenecks 

The Interstate Renewable Energy Council (IREC), an independent nonprofit, engages with state regulators across the nation to improve the process of providing power to EV chargers. This process, known as “energization,” is typically managed by utilities and spans from when the project developer applies for utility approval of their project (the service connection request) to the final connection of that project to the grid. It involves various stakeholders—including customers, site owners (if the site is not owned by the customer), utilities, and local governments—and demands strong communication and coordination. Through our work across the country, IREC has identified common challenges and bottlenecks in the energization process for EV chargers, also known as EV Supply Equipment (EVSE). 

While establishing new service connections is a core business function for utilities, the process often lacks accountability measures to ensure fair and efficient project review. As a result, the process remains somewhat informal and not well-suited to scale at the rate required for significant load growth.  

Lack of transparency is another source of challenges in the energization process. Utilities often do not provide customers with key information, such as whether current grid infrastructure can support projects at particular locations, what grid upgrades may be required, estimates of the associated costs, and projected timelines, before submitting an application for their EVSE project. These issues can leave customers with little visibility into whether their project may be economically viable and whether the energization process timeline will meet their needs. 

While this concern affects all customers wishing to install EVSE, those seeking service connections for MHDEV chargers often face even greater challenges due to the scale and complexity of their projects. To put things in perspective, “a highway charging plaza designed for light-duty EVs—passenger cars, vans, and trucks—can require up to five megawatts of power, enough to power an outdoor sports stadium. A highway stop designed to charge heavy-duty EVs can require thirty megawatts or more, equivalent to the energy needs of a small town!” Because MHDEV charger projects require higher load capacity, infrastructure upgrades are likely to be costly, and the energization process will typically involve additional steps to ensure grid safety and reliability. California utilities report that MHDEV projects requiring distribution grid upgrades can take up to 9 years to interconnect! 

As a leading state in the clean energy transition, California was among the first to confront and navigate EVSE energization challenges for light, medium-, and heavy-duty EVs. California’s ambitious low-emission and zero-emission vehicle regulations, its state goal to achieve carbon neutrality by 2045, and incentives to support the necessary investments have resulted in increased demand for EV charging infrastructure across the state. Due to the challenges described above, the state has experienced significant backlogs of EVSE projects. Evidence suggests that California’s electric utilities may be connecting charging equipment to the grid at a pace that falls short of both growing demand and the requirements of its climate and transportation electrification goals.  

California is no longer the exception. Many states have introduced EV-focused policies, regulations, targets, and incentives that are accelerating EV adoption rates and increasing demand for charging infrastructure. Other states now face EVSE energization delays, similar to those experienced in California.  