Interconnection Equity
Enabling a just and equitable transition to a renewable energy future requires addressing barriers to clean energy adoption that prevent certain groups from accessing clean energy. The interconnection process for clean energy is a significant regulatory barrier that has historically been overlooked.
Interconnection policies (standards) specify the processes, timelines, costs, and technical processes associated with connecting renewable energy systems, energy storage, and other distributed energy resources to the grid. Since early 2024, IREC has been researching how interconnection can serve as a barrier to equitable access to sustainable energy.
Interconnection Equity is the application of energy justice1 to interconnection regulation, with the goal of ensuring that interconnection policies help enable a just and equitable energy transition.
Interconnection equity is an emerging field. Most stakeholders currently engaged in regulatory interconnection proceedings are not fully aware of the link between interconnection and energy equity and justice.
A Collaborative Process to Identify Interconnection Equity Solutions
To investigate how the interconnection may present barriers to under-resourced communities, IREC partnered with Vote Solar to co-facilitate the 2024 convening of its Access and Equity Advisory Committee (AEAC). The AEAC is a mission-driven team of Black, Indigenous and experts of color brought together to “create innovative best practices and policy solutions that enable equitable participation and benefit from clean energy.”
A series of three workshop sessions with the AEAC were convened with a focus on determining how interconnection intersects with energy equity and justice. The sessions had the following objectives:
- Empowering participants to effectively navigate the interconnection process in support of fostering clean energy projects within underserved communities;
- Guiding participants in exercises to help uncover inequitable policies within current interconnection rules and regulations;
- Informing the development of interconnection support materials targeting the specific informational gaps that may be common among energy justice organizations;
- Leveraging the committee’s expertise to draft a list of potential equity-focused interconnection policies that could be used in interconnection proceedings.
IREC also conducted a comprehensive survey of the national interconnection policy landscape and reviewed energy equity academic literature to uncover best practices and opportunity areas.
An overview of the challenges identified through this process, and the potential solutions to these challenges, is included below. A detailed report that can be used as a guide for developing regulatory reforms to reduce interconnection barriers to projects serving under-resourced communities will be released in late 2024.
Barriers to Interconnection Equity & Potential Solutions
In its simplest form, the interconnection process consists of six sequential stages, which can differ in length and complexity depending on project type and size. These steps are explained in the figure below.

The rules that define the technical and procedural requirements of each stage are set by a state’s utility commission, and are then implemented by the electric utility companies. Interconnection customers seeking to develop and interconnect new clean energy or storage projects must have an in-depth understanding of these rules and procedures to effectively participate in the interconnection process. This presents a particular barrier to under-resourced communities.
IREC’s Regulatory Team has been working to identify existing inequities within each interconnection stage and develop potential solutions. These solutions were presented to AEAC members who were tasked with reviewing their efficacy potential and operational feasibility. Feedback was then integrated into the proposed design of each solution.
Below, we provide an overview of each inequity identified and proposed solution. A forthcoming report from IREC will delve into these topics more deeply.

Challenge 1: The Technical and Procedural Complexity of the Interconnection Process
The complexity of the interconnection process—and how challenging this makes it for any community to effectively participate in interconnection—was consistently emphasized by participants in our discovery process.
This complexity includes both technical and procedural complexity. An example of the technical complexity is the fact that applicants may need specialized engineering knowledge needed to identify appropriate sites. An example of procedural complexity is how challenging it can be for many parties to even find the relevant interconnection rules, particularly since even different utilities in the same state may have different policy files that need to be reviewed.
Potential Solution: Providing Subsidized Engineering Support For Community-Led Projects
To address these issues, we recommend that states and utility commissions create programs that subsidize engineering and intervenor2 support staff for community organizations seeking to develop solar or battery energy storage systems.
Such programs should be easily accessible, long enough to support applicants throughout the entirety of the interconnection process, and provide high-quality and specialized technical expertise to accommodate a diverse range of stakeholders.
Challenge 2: A First-In-First-Out Interconnection Queue Approach Disadvantages Under-Resourced Communities
A project’s priority in the interconnection process is determined by its location in the “interconnection queue,” a line/sequence of projects awaiting to be processed, evaluated, and then interconnected into the utility grid.
These queues rely on the first-in-first-out principle in which the first projects to be submitted will be the first to be processed, and therefore the first to reserve the available capacity of existing grid infrastructure.
This means that in order for community projects to be developed without the need for potentially cost-prohibitive upgrades, they must be near the front of the interconnection queue. Unfortunately, in recent years, interconnection queues have grown incredibly long—new projects entering being likely to exceed grid capacity thresholds—just as underserved communities are finally gaining the financial resources to develop their own projects.
Potential Solution: Prioritizing Community-Led Projects Within the Interconnection Queue
One potential solution to these challenges that the IREC team is exploring is the creation of prioritization pathways within the interconnection queue to expedite qualifying projects. Discussions with the AEAC have surfaced some potential concerns with this approach, such as increased likelihood of political backlash against benefiting communities, and the tension between an expedited interconnection process and the time needed for robust community engagement required to ensure projects are developed in a just way.
However, IREC still believes that such a mechanism could be feasible and reduce community exposure to high interconnection upgrade costs and is exploring some of the key design considerations for such a policy.
Challenge 3: Grid Upgrade Costs Present a Significant Barrier to Under-Resourced Communities
Sometimes in the interconnection review process, the utility determines that a proposed project requires grid upgrades in order to ensure safety and reliability of the electric grid. According to the “cost-causation” model applied in most states, the project that triggers the need for these upgrades is required to pay the full cost, even if the upgrades provide benefits to other utility customers. If the project cannot pay the cost of those upgrades, then the project must forfeit its position in the interconnection queue. This creates considerable barriers for community-based projects that are less likely to be able to absorb these costs.
Potential Solution: Distribute Interconnection-Related Grid Upgrade Costs for Projects Serving Under-resourced Communities
To alleviate these burdens, IREC recommends that Commissions establish interconnection upgrade cost recovery programs that distribute the costs of grid upgrades for projects serving under-resourced communities across the Utility’s entire customer base (or at least customers in similar rate classes, such as residential or commercial customers).
Challenge 4: Current Solutions on the Table Are Reactionary in Nature
The potential interconnection solutions described above are ultimately reactionary approaches to addressing interconnection inequities. As a result, they face several implementation challenges that are difficult to design against.
Potential Solution: Address Interconnection Inequities with Proactive Planning
Identify inequities within existing distribution system infrastructure that limit community access to distributed clean energy and electrified buildings and transportation, then invest proactively in upgraded said infrastructure to ensure adoption can be accelerated in those areas. This includes the integration of an equity lens into existing distribution planning metrics, centering community voices and perspectives throughout planning proceedings, and prioritizing infrastructure investments that support accelerated decarbonization, electrification, and clean energy adoption.
Next Steps
In the coming months IREC plans to publish a paper that provides a comprehensive framework for identifying interconnection inequities and makes detailed recommendations on the design of interconnection equity solutions.
Footnotes
- As defined by the Initiative for Energy Justice, “Energy justice refers to the goal of achieving equity in both the social and economic participation in the energy system, while also remediating social, economic, and health burdens on those historically harmed by the energy system (“frontline communities”). Energy justice explicitly centers the concerns of marginalized communities and aims to make energy more accessible, affordable, clean, and democratically managed for all communities. The practitioner and academic approaches to energy justice emphasize these process-related and distributive justice concerns.
- Refers to third-party mediators who facilitate discussions around interconnection process disputes.